International Tower Hill Mines Ltd. ("ITH" or "the Company") (TSX VENTURE: ITH)(NYSE-A: THM)(FRANKFURT: IW9) is pleased to announce the results of its independently prepared mid-year mineral resource estimate for the Money Knob deposit at its Livengood gold project near Fairbanks, Alaska. The independent study incorporates approximately half the drilling that has been completed on the property in 2008. The Company anticipates a further major expansion of the open-ended resource when the results from the outstanding drilling are returned and an 'end-of-program' resource estimate is completed in mid-first quarter 2009. In addition, the Company is very pleased to see such a large percentage of the estimated resources upgraded to the indicated category (approximately 45% indicated resources and 55% inferred resources), noting that the average grade of the previous 2007 inferred resource increased significantly in the 2008 indicated resource (a 17% increase in grade), see Table 1.
Table 1
Comparison of Livengood Resources from 2007 and 2008 (at 0.50 g/t gold
cutoff)
---------------------------------------------------------------------------
Au Cutoff Tonnes Au Million
Year Classification (g/t) (millions) (g/t) Ozs Au
---------------------------------------------------------------------------
2007 Inferred 0.50 82.88 0.71 1.889
---------------------------------------------------------------------------
2008 Indicated 0.50 69.53 0.83 1.860
---------------------------------------------------------------------------
Inferred 0.50 87.88 0.77 2.170
---------------------------------------------------------------------------
This new data confirms the Company's belief that the Livengood Deposit has an excellent possibility to become one of North America's largest new gold discoveries. The pre-eminent gold endowment of the system is strongly illustrated by a 95% increase in the overall gold ounces when calculated at a 0.30 g/t cutoff (Table 2) and a 160% increase in the overall gold ounces when calculated at a 0.7 g/t gold cutoff. This increase dramatically highlights the overall grade increase of the estimated resource in the deposit (Table 3).
Table 2
Comparison of Livengood Resource from 2007 and 2008 (at 0.30 g/t gold
cutoff)
---------------------------------------------------------------------------
Au Cutoff Tonnes Au Million
Year Classification (g/t) (millions) (g/t) Ozs Au
---------------------------------------------------------------------------
2007 Inferred 0.30 188.01 0.54 3.269
---------------------------------------------------------------------------
2008 Indicated 0.30 138.54 0.61 2.730
---------------------------------------------------------------------------
Inferred 0.30 205.78 0.55 3.640
---------------------------------------------------------------------------
Table 3
Comparison of Livengood Resource from 2007 and 2008 (at 0.70 g/t gold
cutoff)
---------------------------------------------------------------------------
Au Cutoff Tonnes Au Million
Year Classification (g/t) (millions) (g/t) Ozs Au
---------------------------------------------------------------------------
2007 Inferred 0.70 33.23 0.93 0.985
---------------------------------------------------------------------------
2008 Indicated 0.70 36.37 1.06 1.240
---------------------------------------------------------------------------
Inferred 0.70 42.78 0.96 1.320
---------------------------------------------------------------------------
Livengood Project Highlights
- Independent study notes that the Livengood Deposit has significant expansion potential beyond its current 1.86M ounce indicated and 2.17M ounce inferred gold resource estimate (at 0.5 g/t gold cutoff), with assay results still pending for many drill holes and the deposit remaining open in all directions.
- New deep and eastern step out drill holes to the Core Zone have intersected thick alteration zones, highlighting the potential for significant near-term expansions of the deposit.
- Preliminary metallurgical information shows favourable cyanide solubility for possible heap leaching with increasing recoveries at finer crush sizes offering milling potential of the higher grade areas.
- The project has a favourable logistical location and no major permitting hurdles have been identified to date.
These highly encouraging results have resulted in a decision by the Company to implement a major winter drilling project, now planned to commence in February 2009, which will test immediate high-grade Core Zone expansion targets directly to the east of the main body mineralization (for example, one hole along southern margin of the winter target area - MK-RC-0050 - returned 79.3 metres @ 1.16 g/t gold).
In addition, a drilling program is planned for summer 2009 to continue with the expansion of the deposit in the newly discovered Deep and Far East zones as well as the deposit in general. Modeling of the existing drill data with surface geochemistry has identified a new target area to the south-west of the Core Zone that will be tested in February, 2009. If these new large areas of surface gold return positive results it could double the area of mineralization currently outlined in the existing resource estimate. Following the anticipated completion of the winter drilling in the second quarter of 2009 the Company plans to complete an updated 2009 resource estimate that will be used in a preliminary economic assessment of the deposit currently planned for mid-2009. A budget of approximately CAD $6M has been planned for the winter and summer programs in 2009.
To view Figure 1 accompanying this press release, please click on the following link: http://media3.marketwire.com/docs/ith1029.jpg
The Company wishes to emphasize that the Livengood project has a very favourable logistical location, being situated 110 road kilometres north of Fairbanks, Alaska along the paved all weather Elliot Highway and the Trans Alaska pipeline corridor and approximately 55 kilometres north of the Alaska State power grid and along the proposed Alaska natural gas pipeline route.
The Company is currently engaged in the cyanide extraction analysis of numerous samples from both the oxide and non-oxide mineralized zones and, although this data is still preliminary, it indicates that both types of mineralization have the potential for heap leach extraction and that significant increases in recovery may be obtained with finer crushing (thus suggesting that milling of the higher grade areas of the deposit would be beneficial).
Currently, the Company estimates that less than 30% of the known shallow mineralized zone (down to 200 metres) has been effectively drill tested. The Livengood target is open in all directions as well as at depth, with many of the recent deeper holes intersecting mineralization in the underlying lower sedimentary package (such as MK-RC-0023 with 57.9 metres @ 2.51 g/t gold and MK-RC-0060 with 82.3 metres @ 1.07 g/t gold). A 3D image of the most recently released Livengood drill information can be viewed at: http://www.corebox.net/properties/livengood.
As a comparison, the Fort Knox mine, one of North America's larger gold mines located 80 kilometres to the southeast of Livengood, reported in their March 30, 2007 43-101 technical report a proven and probable resource estimate of 159Mt at an average grade of 0.53 g/t gold (the current mid-year Livengood resource significantly exceeds Fort Knox at this time). The Fort Knox mine has announced that they are currently commissioning a large run of mine heap leach facility to augment their current milling operations, and estimates an average heap leach recovery of 61%. The Fort Knox mine reported 2007 gold production of 338,459 ounces at a life of mine cash cost of approximately $390/ounce. However, the Company cautions that this information with respect to the Fort Knox property and operations could not be verified by the Company and is not necessarily indicative of the mineralization on the Livengood Property or the potential production from, or cost of, any future mining of the Livengood Property.
Project Background
ITH controls 100% of its 44 square kilometre Livengood land package, which is primarily made up of leased land from the Alaska Mental Health Trust and a number of smaller private mineral lessors. The Company and its predecessor, AngloGold Ashanti (U.S.A.) Exploration Inc., have been exploring the Livengood area since 2003, with the project's first indicated resource estimate being announced in early 2008. The 2008 drilling program marks the first grid drilling resource definition campaign for the project and is only the initial step in what the Company envisions as a major long-term exploration program to define what it anticipates is one of the world's largest new gold deposits.
Results of the Geologic Review and Resource Estimate
Geological Review
On October 28, 2008 Giroux Consultants Ltd. and Mineral Resource Services Inc. delivered the final draft of their technical report on the Livengood project (the "Report"), which includes information regarding the mineral resource estimate and 2008 surface exploration completed to the date of the Report. The information describes gold mineralization in the deposit and possible ore controls. Primary ore controls appear to be the intersection of favourable host lithologies with major structural zones which are interpreted to have acted as conduits for intrusion-related gold bearing fluids. The volcanic, sedimentary and mafic rocks are favourable host rocks and are persistently mineralized. Mineralization in the Money Knob deposit occurs at surface and forms stratabound and cross-cutting bodies in a large thrust faulted and recumbently folded sedimentary and volcanic sequence. The main body of mineralization lies within a general 2 kilometre wide, 6 kilometre long northeast trending belt, with the current Core Zone focused along a northwest trending surface geochemical anomaly that is at least 1.6 kilometres long and 800 meters wide. This large structural zone has localized a series of 90 million year old (Fort Knox age) dikes, sills and plugs that are believed to be related to the gold mineralization. The configuration and thickness of the mineralized zones suggest a near-surface, low strip, bulk-mining scenario.
Resource Estimate
The indicated and inferred mineral resource estimate for the Livengood deposit covers an area of approximately 3.6 square kilometres and is based on 116 drill holes which have an average length of 217 meters and 11 trenches with an average length of 45 metres.
Approximately one third of the total estimated area (1.1 square kilometres) contains 98 of the drillholes and, in this area, the geology has been modeled to represent the volumes of the different stratigraphic units on the property. Outside of the modeled area all the data was grouped together because there was insufficient geological control for more detailed analysis. Statistically, each of the geological volumes was treated independently with individual capping grades applied. However, the populations were not sufficiently different to be kriged independently.
Variogram modeling was done using 5 metre composites, the variography showed excellent continuity downdip and across dip with lesser continuity along strike. Bulk density was estimated on the basis of individual density measurements made on core samples and reverse circulation drill chips from each stratigraphic unit. In total, 95 measurements were used. Based on the general geology, a bulk density of 2.68 was used for the area outside the modeled volume. In the model, blocks with dimensions of 20 x 20 metres horizontal and 5 metres vertical were estimated by ordinary kriging.
The geology of the holes which still have assays pending suggests that the favourable host stratigraphy and alteration remain open laterally and at depth, thus indicating that the system could potentially be much larger than the current estimate.
Qualified Person and Quality Control/Quality Assurance
The work program at Livengood was designed and is supervised by Dr. Russell Myers, Vice President of Exploration, and Chris Puchner, Chief Geologist (CPG 07048) for ITH who are responsible for all aspects of the work, including the quality control/quality assurance program. On-site personnel at the project log and track all samples prior to sealing and shipped to ALS Chemex for assay. ALS Chemex's quality system complies with the requirements for the International Standards ISO 9001:2000 and ISO 17025:1999. Analytical accuracy and precision are monitored by the analysis of reagent blanks, reference material and replicate samples. Quality control is further assured by the use of international and in-house standards. Finally, representative blind duplicate samples are forwarded to ALS Chemex and an ISO compliant third party laboratory for additional quality control.
Dr. Paul D. Klipfel, Ph.D., AIPG, a consulting economic geologist employed by Mineral Resource Services Inc., has acted as the Qualified Person, as defined in NI 43-101, for the exploration data and supervised the preparation of the technical exploration information on which some of this news release is based. Dr. Klipfel has a Ph.D. in economic geology and more than 28 years of relevant experience as a mineral exploration geologist. He is a Certified Professional Geologist (CPG 10821) by the American Institute of Professional Geologists. Both Dr. Klipfel and Mineral Resource Services Inc. are independent of the Company under NI 43-101.
Mr. Gary Giroux, MASc., P. Eng (B.C.), a consulting geological engineer employed by Giroux Consultants Ltd., has acted as the Qualified Person, as defined in NI 43-101, for the Giroux Consultants Ltd. mineral resource estimate. He has over 30 years of experience in all stages of mineral exploration, development and production. Mr. Giroux specializes in computer applications in ore reserve estimation, and has consulted both nationally and internationally in this field. He has authored many papers on geostatistics and ore reserve estimation and has practiced as a Geological Engineer since 1970 and provided geostatistical services to the industry since 1976. Both Mr. Giroux and Giroux Consultants Ltd. are independent of the Company under NI 43-101.
The Report will be finalized and filed on SEDAR within 45 days of the date of this news release.
About International Tower Hill Mines Ltd.
International Tower Hill Mines Ltd. is a resource exploration company, focused in Alaska and Nevada, which controls a number of exploration projects representing a spectrum of early stage to the advanced multimillion ounce gold discovery at Livengood. ITH is committed to building shareholder value through new discoveries while maintaining a majority interest in its key holdings, thereby giving its shareholders the maximum value for their investment.
On behalf of INTERNATIONAL TOWER HILL MINES LTD.
Jeffrey A. Pontius, President and Chief Executive Officer
Cautionary Note Regarding Forward-Looking Statements
This press release contains forward-looking statements within the meaning of Section 27A of the Securities Act and Section 27E of the Exchange Act. All statements, other than statements of historical fact, included herein including, without limitation, statements regarding the anticipated content, commencement and cost of exploration programs, anticipated exploration program results, the discovery and delineation of mineral deposits/resources/reserves, business and financing plans and business trends, are forward-looking statements. Information concerning mineral resource estimates also may be deemed to be forward-looking statements in that it reflects a prediction of the mineralization that would be encountered if a mineral deposit were developed and mined. Although the Company believes that such statements are reasonable, it can give no assurance that such expectations will prove to be correct. Forward-looking statements are typically identified by words such as: believe, expect, anticipate, intend, estimate, postulate and similar expressions, or are those, which, by their nature, refer to future events. The Company cautions investors that any forward-looking statements by the Company are not guarantees of future results or performance, and that actual results may differ materially from those in forward looking statements as a result of various factors, including, but not limited to, variations in the nature, quality and quantity of any mineral deposits that may be located, the Company's inability to obtain any necessary permits, consents or authorizations required for its activities, the Company's inability to produce minerals from its properties successfully or profitably, to continue its projected growth, to raise the necessary capital or to be fully able to implement its business strategies, and other risks and uncertainties disclosed in the Company's annual report on Form 20-F filed with the United States Securities and Exchange Commission (the "SEC"), and other information released by the Company and filed with the appropriate regulatory agencies. All of the Company's Canadian public disclosure filings may be accessed via www.sedar.com and its United States public disclosure filings may be accessed via www.sec.gov, and readers are urged to review these materials, including the technical reports filed with respect to the Company's mineral properties.
Cautionary Note Concerning Reserve and Resource Estimates
This press release and other information released by the Company uses the terms "resources", "inferred resources" and "indicated resources". United States investors are advised that, while such terms are recognized and required by Canadian securities laws, the SEC does not recognize them. Under United States standards, mineralization may not be classified as a "reserve" unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. Mineral resources that are not mineral reserves do not have demonstrated economic viability. United States investors are cautioned not to assume that all or any part of inferred or indicated resources will ever be converted into reserves. Inferred resources, in particular, have a great amount of uncertainty as to their existence and as to whether they can be mined legally or economically. It cannot be assumed that all or any part of the inferred or indicated resources will ever be upgraded to reserves. Therefore, United States investors are also cautioned not to assume that all or any part of the inferred or indicated resources exist, or that they can be mined legally or economically.
National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101") is a rule developed by the Canadian Securities Administrators, which established standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Unless otherwise indicated, all resource estimates contained in this press release have been prepared in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum (the "CIM") Standards on Mineral Resource and Mineral Reserves, adopted by the CIM Council on November 14, 2004 (the "CIM Standards") as they may be amended from time to time by the CIM. United States shareholders are cautioned that the requirements and terminology of NI 43-101 and the CIM Standards differ significantly from the requirements and terminology of the SEC set forth Industry Guide 7. Accordingly, the Company's disclosures regarding mineralization may not be comparable to similar information disclosed by companies subject to the SEC's Industry Guide 7. Cautionary Note Regarding Similar Mineral Property References
This press release contains information with respect to adjacent or similar mineral properties in respect of which the Company has no interest or rights to explore or mine. The Company advises US investors that the US Securities and Exchange Commission's mining guidelines strictly prohibit information of this type in documents filed with the SEC. Readers are cautioned that the Company has no interest in or right to acquire any interest in any such properties, and that mineral deposits on adjacent or similar properties are not indicative of mineral deposits on the Company's properties.
This press release is not, and is not to be construed in any way as, an offer to buy or sell securities in the United States.
NR08-22
The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of the contents of this press release, which has been prepared by management.
Contacts:
International Tower Hill Mines Ltd.
Quentin Mai
Vice-President - Corporate Communications
Toll Free: 1-888-770-7488 or (604) 683-6332
(604) 408-7499 (FAX)
Email: qmai@internationaltowerhill.com
Website: www.internationaltowerhill.com
SOURCE: International Tower Hill Mines Ltd.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment